Saturday, December 29, 2007
interior paint and smooth subfloor
Thursday, November 15, 2007
final stucco and sheetrock

view from driveway entrance

view of south east corner at front of house
The stucco turned out very nice. The company that did the work really did do a great job. Now the real question seems to be how to keep the other subs from leaning 200 lb stacks of sheetrock up against it and scratching it. The door subcontractor drove a shim right through the exterior of the stucco from the inside trying to install a door. I've already spoken with the stucco sub and he tells me that he'll be back out at the end to do any patch work that will invariably need to be done after the other subs have done their damage.

garage view almost sheetrocked

living room looking toward front door

view from kitchen looking into dining room
The sheetrockers have really been working fast. I think that they will be completely done within the next few days. Unfortunately they had me call for the drywall inspection and when the inspector showed up they were'nt ready for him and he failed it. I'll call again today to have it re-inspected tomorrow. Once the sheetrock is all taped, then they will texture and then I can have it painted. Everything is coming together rather quickly now. This is good as I really need to get this house finished up.
Tuesday, October 30, 2007
stucco & mechanical units

Monday, October 8, 2007
lath and batts

the big hiccup is that i forgot to realize that exterior door jambs need to go in before the stucco is applied and therefore now am waiting on those to be installed. they should go in today (keeping fingers crossed).

the other mild hiccup is that the 27' slider that was to be installed on friday was not because the company that produced the door has either misplaced one of the side jambs or failed to ever make it. regardless, they are making a new one and having it powder-coated monday for install on tuesday. notice the door panels for the giant slider in the distance of the photo below.

the insullation was also installed at some point between saturday night and sunday morning. they told me that they would be in to do it during the night on saturday but i didn't believe them. but they did. as you can see in the pictures it is all finished. the next major step is sheetrock which will really define the spaces in the house.
Tuesday, October 2, 2007
paper on the roof
In addition to the roof, the stucco contractor continues to make progress. The first layer of mud should get sprayed on Monday. The whole process should take about 2 weeks as they require a 5-7 day curing period between the 3 coats.
Friday, September 28, 2007
stucco start


This week was also a big week for inspections. We had mechanical, electrical and plumbing roughs inspected Monday along with the framing rough. Unfortunately only the electrical passed. The mechanical failed because the inspector said a strap was missing on the chimney flue (it was there all along, just up in the chimney where he couldn't see it). The plumbing failed because the plumbing contractor is using a new style of washing machine drain box that the inspector had never seen before and didn't think it was up to code. It is. Framing failed because the framers forgot to nail half of the truss hangers to the glu-lam over the kitchen. needless to say, I'm really glad the inspector caught that one. Wednesday we passed roof sheating and shear wall and gas piping. So yesterday I called the mechanical, plumbing and framing roughs again and again they failed - stupidly for the same reasons. This morning the fireplace contractor was out there putting ANOTHER strap where the inspector can simply look up and see it. In the meantime, I need to call the inspector and explain to him that the other items are allowed, just new to him. Hopefully I'll be able to call new inspections for Monday and finally get everything passed off.
The roofers should be starting today as well. I'll post pictures of their progress as soon as they make some.
Monday, September 24, 2007
interiors



Monday, September 17, 2007
the floorplan i fell in love with
- master bathroom - made it larger with a separate water closet, double sink, steeping tub, steam shower and skylight.
- kitchen/dining room - knocked down wall between. made window at kitchen sink larger. added window in dining room. added pantry.
- living room - added a 27' long sliding glass door into courtyard.
- second bath - turned two bathrooms between bedroom 2 and 3 into a single jack-n-jill bathroom.
- playroom - added windows and increased size of existing windows.
- garage - added third car bay and changed from double garage door to three single car garage doors.
- carport - added carport to address issue of distance between garage and kitchen.

pool in the courtyard




pinkHAUS found
We found this house after a year or so of casually looking in the area for a house to buy and POSSIBLY fix up if necessary. Well, needless to say, we ended up purchasing this one with the thought that we would spend a little money and fix it up. The reason that this house appealed to us so much is that it has a great floorplan around a courtyard with a swimming pool in the middle of the house. It also sits on a full acre of land - something quite rare in Las Vegas these days.
Here's a picture of the kitchen at the very early stage of demolition. And here's another picture of the kitchen (this side of the red pick-up) after demolition. At this point it looks like a brand new house that has recently started being framed.









